Impact of scheduler settings on total imaging time corrected
Summary: Scheduler settings like tracking, focusing, aligning and guiding are calculated only once per schedule and not multiplied by the number of open iterations, which led to exaggerated estimations.
Test Plan:
- Activate the scheduler setting "Remember job progress.
- Create a schedule with completion condition "Repeat for x runs".
- Do not activate the steps for tracking, focussing etc.
- Modify the schedule and check, that the estimated duration varies by 1-2 min, whenever you activate or deactivate one of the steps.
Reviewers: mutlaqja, TallFurryMan
Reviewed By: mutlaqja
Subscribers: kde-edu
Tags: KDE Edu
Differential Revision: https://phabricator.kde.org/D21073